Please see below update for works completed Week Ending 11th January 2026 (Week One)
- Works commenced on Monday 5 January 2026 under a road closure.
- 100 metres of new water main successfully installed.
- Complete preparatory excavations for the installation of 500 metres of new pipeline.
- Install 500 metres of new water main following completion of preparatory works.