Update 1 for the water main works at Halfpence Lane

1/12/2026

0 Comments

 
Please see below update for works completed Week Ending 11th January 2026 (Week One)
  • Works commenced on Monday 5 January 2026 under a road closure.
  • 100 metres of new water main successfully installed.
Works Scheduled for January
  • Complete preparatory excavations for the installation of 500 metres of new pipeline.
  • Install 500 metres of new water main following completion of preparatory works.